suhul albab and atadif

Area: 6664 hectares
The lands of the Tadf and Al-Bab irrigation project are located within the bed of the Gold River in the province of Aleppo, and the southern borders of the project are 40 km to the north-east of the city of Aleppo. Length / 33 / km

The project consists of

  1. The water outlet facility is equipped with two gates that control the water to the supply channel
  2. The supply channel has a length of 3.156 km and a flow of 5.167 m3/s, with a trapezoidal section covered with concrete
  3. GRP Tubular Main Ducts
  4. Tubular irrigation network of GRP and polyethylene pipes of different diameters and a total length of (232 km)
  5. Drainage network of P.V.C pipes with a length of 20 km
  6. Road network parallel to tube irrigation canals
  7. Three pumping stations and three electrical transfer stations with three suction basins


Design Irrigation System and Total Irrigation Efficiency: Modern irrigation with a pipe network that ensures the operation of modern irrigation networks (with an efficiency of 79%)

As for the drainage system: the network of open drainage and covered drainage was implemented with the implementation of the project.